| January 27, 2003 |
Vaughan Council creates the Vaughan Health-Care Facility
Study Task Force.
|
|
|
| March 31, 2003 |
Council approves the composition of the Task Force.
|
|
|
| April 29, 2003 |
Inaugural meeting of the Vaughan Health-Care Facility Study
Task Force.
|
|
|
| June 10, 2003 |
The Task Force authorizes the preparation of terms of reference
for a consulting study to form the basis for a request to
the Ministry of Health and Long Term for its support for further
work on a Vaughan Health-Care Facility. The Task Force also
appoints a “Consultant Search Sub-Committee”.
|
|
|
| September 22, 2003 |
Council authorizes the Task Force to proceed with “The
Vaughan Health-Care Facility Planning and Implementation Study”
and to report back to Council for the purposes of obtaining
ratification of the Task Force’s recommendation.
|
|
|
| November 27, 2003 |
Terms of reference for the study are issued, with a closing
date of January 15, 2004 for the submission of proposals.
|
|
|
| January 15, 2004 |
A total of six proposals were received. The Consultant Search
Sub-Committee evaluated the proposals and selected two proponents
for interviews, which were held on February 5, 2004. The sub-committee
selects the proposal from IBM Business Consulting Services
and GPC International.
|
|
|
| February 19, 2004 |
The full Task Force meets to consider the recommendation
of the Consultant Selection Sub-Committee. The Task Force
ratifies the recommendation of the sub-committee and directs
that its recommendation proceed to Vaughan Council for its
consideration.
|
|
|
| February 23, 2004 |
Vaughan Council ratifies the Task Force’s selection
of IBM Business Consulting Services and GPC International
as the consulting team to be retained to conduct the “The
Vaughan Health-Care Facility Planning and Implementation Study”.
|
|
|
| June 15, 2004 |
Task Force Meeting with the Partner’s Working Group,
including a presentation by the consulting team on the initial
findings of the study.
|
|
|
| July 28, 2004 |
The consulting team conducts a Visioning Session with the
Task Force.
|
|
|
| October 19, 2004 |
The Task Force meets to review supporting data for the study,
obtain validation for the vision for the health-care facility
and to provide direction to proceed with the drafting of the
study; and to obtain authorization to hold a public information
meeting.
|
|
|
| November 16, 2004 |
A Public Information Meeting is held in the Council Chambers,
with a presentation by IBM Business Consulting Services.
|
|
|
| December 13, 2004 |
Receipt of draft “Vaughan Health-Care Facility Planning
and Implementation Study”. Study sent to Task Force
members for their review in advance of the next meeting.
|
|
|
| January 18, 2004 |
The Task Force Meets to finalize the study for submission
to Vaughan Council. On review, the Task Force directed that
additional work be undertaken and that the revised report
be submitted to a Task Force meeting on Tuesday, February
22, 2005.
|
|
|
| February 22, 2005 |
After consideration of the revised study, the Task Force
adopted a resolution approving the draft “Vaughan Health-Care
Facility Planning and Implementation Study”. Direction
was given to finalize the study and that it be submitted to
Vaughan Council for its endorsement and action. The Task Force’s
resolution forms Appendix 4.
|
|
|
| February 28, 2005 |
Vaughan Council, in consideration of the recommendation
of the Task Force, unanimously approved the Vaughan Health-Care
Facility Planning and Implementation Study and that the document
be prepared for submission to the Province. Council directed
that the study be submitted to the Minister of Health and
Long-Term Care as the basis for Vaughan’s request to
the Ministry for its support and authorization to proceed
with the planning and development processes for a health-care
facility in the City of Vaughan. It was also directed that
the study be forwarded to the Regional Municipality of York
with the request for its support in principle for the study.
Vaughan Council’s resolution forms Appendix 5.
|
|
|
| March 31, 2005 |
The Council of the Regional Municipality of York considered
the request from Vaughan Council for its support. Regional
Council adopted a resolution supporting in principle the actions
contained in the Vaughan Council resolution of February 28,
2005. In addition, it included advice to the Minister of Health
and Long-Term Care that the Region of York is committed to
working in partnership with all the stakeholders throughout
the planning and development processes for the proposed facility.
A copy of the resolution forms Appendix 6. |